In this article we explain Brickwork Calculation. How many nos of bricks, cement bags and sands are required for 1m3 Brick Masonry. How many quantity of mortar required for 1m3 brick work, etc. It is very common question which is mostly ask in interview and other competitive exam.
As well as the nos of bricks, cement bags for various quantity is a very general knowledge in civil engineering field. Finding quantity of bricks, sand, and cement for different works is very easy.
Table of Contents
Brickwork Calculation for 1m3:
Suppose we construct the wall having a volume of the 1m3, the size of brick is 190 mm ×90 mm ×90 mm and the mortar is 10 mm thick with the ratio of 1 : 6. So
Steps
- How many nos of brick used in 1m3 without mortar
- How many nos of brick used in 1m3 with mortar
- Quantity of mortar for 1m3 volume
- Quantity of cement and sand
- Quantity of cement and sand in KG
Calculation data:
- Size of brick without mortar = 19cm X 9cm X 9cm
- Size of brick with mortar = 20cm X 10cm X 10cm
- Cement to Sand proportion = 1 : 6
- Mortar thickness = 10mm
- Volume of brick wall = 1m3
How many nos of brick used in 1m3 without mortar (steps-1):
Size of brick without mortar = 19cm X 9cm X 9cm
Converting size centimetre to meter. Use google conversion tool for converting dimension
Size of brick is = 0.19m X 0.09m X 0.09
Volume of 1 brick without mortar = 0.001539m3
Volume of brick wall = 1m3
Nos of bricks used in 1m3
= volume of brick wall /volume of 1 brick without mortar
= 1/0.001539
= 649.77
= 650 Nos of brick used in 1m3 volume without mortar
How many nos of brick used in 1m3 with mortar (steps-2):
Size of brick with mortar = 20cm X 10cm X 10cm
Converting size centimetre to meter. Use Google conversion tool for converting dimension
Size of brick in meter = 0.2m X 0.1m X 0.1m
Volume of 1 brick with mortar = 0.002m3
Volume of brick wall = 1m3
Nos of bricks used in 1m3
= volume of brick wall /volume of 1 brick with mortar
= 1/0.002
= 500
= 500 Nos of brick used in 1m3 volume with mortar
Quantity of mortar for 1m3 volume (step-3)
The volume of brick used in 1m3 with mortar
= 500 X 0.19 X 0.09 X 0.09
=0.77m3
Therefore,
Volume of mortar in wet condition used in 1m3 brick masonry
= volume of wall – volume of brick with mortar
= 1-0.77
= 0.23m3
Increase 15% volume of wet mortar for wastage and filling in frogs.
Total Volume of wet mortar
= (0.15 X 0.23) + 0.23
= 0.264m3
Due to pouring water in dry mortar, reduces its 25% volume
Volume of dry mortar
= 0.264 + (0.25 X 0.264)
=0.33m3
Therefore, 0.33m3 volume of dry mortar required for 1m3 brick masonry.
Quantity of cement and sand (step-4)
Volume of brick masonry
=1m3
Cement to sand proportion = 1 : 6
Therefore,
Volume of dry Mortar
= 0.33m3
Volume of 1bags cement = 0.035m3 (where weight of 1bags = 50kg)
Sum of proportion of cement to sand
= 1+6
=7
Nos of cement bag
=((total volume of cement )/(volume of 1bag of cement)
= ((1/7) X 0.33) / 0.035)
= 1.347 bags which is similar to 2bags
Quantity of sands
= (6/7) X 0.33
= 0.283m3
Quantity of cement and sand in KG (step-5)
Weight of cement
= density of cement X total volume of cement
=1440 X ((1/7) X 0.33)
=67.88KG
Weight of sand
= density of sand X total volume of sand
=1600 X 0.283
=452.8KG
Hope you found the article and Calculator useful. Share this Calculator with your Friends | Sharing is Caring. Click on Red notification bell at the bottom right and allow notifications. Stay tuned!
Also Read:
- Foundation Excavation Rate Analysis Excel Sheet
- Sand Filling In Foundation Rate Analysis Spread Sheet.
- Brick Bats Cement Concrete (1:4:8) Rate Analysis Excel Sheet.
- First Class Brick Masonry Work Rate Analysis Sheet.
- Reinforced Cement Concrete (1:2:4) Work Rate Analysis Spreadsheet.
- Reinforced Cement Concrete (1:1.5:3) Work Rate Analysis Spreadsheet.
- 12mm Thick Cement Plastering Work Rate Analysis sheet
- 20mm Thick Cement Plastering Work Rate Analysis sheet
- 3 Coats White Washing Work Rate Analysis Spreadsheet
- RCC DESIGN EXCEL
- BEAM DESIGN EXCEL DOWNLOAD FREE